WJ News

Latest News and Updates from WJ Groundwater and across the Industry.

Hamad-Airport-doha-mezzanine-level.jpg

Hamad International Airport Station Box

Precision. Accuracy. Patience

Hamad Airport DohaThe Hamad International Station Box is a sub-surface structure composed of (approximately) a 305m long by 25m wide by 20m deep box with two abutting single level MEP zones approximately 10m deep. The Station Box is directly adjacent to the airport lagoons which are connected to the Arabian Gulf. The groundwater table has been encountered at about +0.5m QNHD, or about 2.5m below the current ground level.  Excavation of the box was done using a top-down method.

Part of the requirements in the construction of the station box is monitoring the movement or behaviour of the structural elements such as the diaphragm wall, concrete beams, plunged columns and temporary steel props; and the movement of the ground and nearby structures surrounding the box.

Automated In-place bi-axial inclinometers were used to monitor wall deflection, both the x and y directions. These instrument record sub-millimeter movement of the diaphragm wall on an hourly interval, and the data were instantaneously processed and the results were accessible at almost real time.  The In-place Inclinometers were also supplemented by manual inclinometer which were surveyed 3x a week.  Ground settlement were monitored using precise levelling, and wall movement of the nearby bridges were monitored using 1” (one-second) Total Station.

Hamad Airport Doha groundwater modellingVibrating wire strain gauges were used to monitor the load of the concrete beams, plunged columns and the temporary props. These instruments were hard-wired to dataloggers, which sends all the data remotely to a central monitoring PC. An audio-visual alarm was also connected to the datalogger, which tripped whenever the set limit is breached. The amber trigger limits were breached several times, but no red trigger limit was ever encountered.

During the excavation stage, the Monitoring Group consisting of Group Five’s Project Manager and WJ’s expert reporter convened daily to discuss the results of the monitoring.

Precision.  Accuracy.  Patience. Confidence!

MAIN CONTRACTOR:  Group Five Construction
ENGINEER: Mott MacDonald
PROJECT MANAGER: MACE
CLIENT:  NDIA Steering Committee,

read more
WJ Groundwater AdminHamad International Airport Station Box
Pipeline-wellpoint-dewatering-dubai-airport.jpg

Dubai International Airport dewatering stormwater pipe line excavation

WJ Groundwater have completed several projects at Dubai International Airport. This commission saw us use wellpoints to dewater the length of a new stormwater and fuel line that was being installed by ALEC at the Dubai International Airport.

WJ installed a single sided wellpoint system to provide the Main Contractor with clear access to the trench from one side to undertake excavation work and to install the storm water pipeline and fuel line without obstructions. As ALEC wanted a quick installation and speedy drawdown, instead of using conventional jetting techniques, the wellpoints were installed using WJ’s SM14 rotary drilling rig. The trench was dug in the open with stepped face to maintain stability. WJ were chosen to undertake the works as they have been working on the airport for over 10 years and have considerable knowledge of the ground conditions, were extremely competitive, and maintain up to date landside and airside gate passes for their dedicated airport engineers and technicians.

The project went extremely well and the engineers on site were impressed by the tidiness of the installation. WJ used diesel wellpoint pumps connected to a central headermain to draw the water out of the ground. Contact WJ Groundwater today to find out how we can assist you with pipeline dewatering.

read more
WJ Groundwater AdminDubai International Airport dewatering stormwater pipe line excavation
Dubai-Internationial-Airport-Terminal-3.jpg

Dubai International Airport Terminal 3 and Concourses

Dubai, iconic for its high rise buildings including the World’s tallest building, the Burj Khalifa, is the business hub and holiday destination of the Middle East.

Dubai Internationial Airport Terminal 3 aTo build itself as major transport hub for passengers and cargo travelling across the globe, in 2002 Dubai’s Department of Civil Aviation (DCA) initiated construction of the Dubai Airport Terminal 3 building and concourses 2 and 3. It covered a massive area of 750m by 500m and was excavated up to 25m deep. When it was completed in 2008 the Terminal 3 building was the largest building in the world per floor space and is currently the largest terminal in the World. The Terminal 3 iconic building is constructed to look like an aeroplane wing, and initially was exclusively for Emirates airlines.

To help realise this fantastic engineering ambition, WJ Groundwater were, of course, brought onto the team.

To facilitate the excavation works in the dry, WJ Groundwater used its considerable experience dewatering large scale project in Europe installed a large scale dewatering system.  A key selling point of WJ Groundwater’s solution was that despite the sheer scale of the project, all the deepwells were installed around the perimeter of the site. This meant that the Main Contractor could get on with the excavation and construction works without having any obstructions. At peak construction WJ were operating in excess of 200 deepwells as well as a fully automated data logger monitoring system that allowed WJ and their clients to monitor water levels across site in real time from a website.

WJ Groundwater is very proud of their achievements and is honoured to have worked on such an iconic project.

  • LOCATION: Dubai, United Arab Emirates
  • CLIENT: Dubai Airports Company, Government of Dubai
  • MAIN CONTRACTOR: Al Naboodah Contracting
read more
Neil.CoulterDubai International Airport Terminal 3 and Concourses